The smoke prevention partition system and the smoke prevention equipment system are tested in the field and in the fire control room as follows to check the working status of the entire system.
1. Start the blower group on site; remotely start the blower; automatically start the blower;
2, start the positive pressure air supply system, and check the air outlet (valve) is normal and effective;
3. Start the exhaust fan on site; remotely start the exhaust fan; automatically start the exhaust fan. Check whether the fire dampers of the air conditioning system and the ventilation system are self-locking.
4, manually open and reset the smoke outlet (valve) is open and normal;
5, check the test smoke wall; (automatic manual two ways)
6, detection system linkage test function. Given the signal of a certain area, it is effective to see whether the function of the fire prevention partition facility (fire door, fireproof window, fire prevention curtain, fire damper,) of this fire prevention partition is intact.
7, in the place to check, pay attention to whether or not to block the smoke outlet and obstruct the smoke wall activities obstacles.
8. Check whether the smoke window at the height of the site is flexible and easy to use.